Field notes: the pad site that penciled until the drainage easement showed up

A shopping cart left in an empty parking lot in front of a low commercial building, with a stop sign nearby.

We had a pad site in front of a grocery-anchored center that penciled clean. QSR user, strong traffic count on the arterial, a curb cut already approved from the original PUD. The broker's site plan showed a 0.9-acre parcel, full building footprint, drive-thru stacking that fit without even trimming the landscape buffer. LOI went out on a Thursday.

The title commitment came back the following week with an easement nobody on our side had flagged: a 30-foot drainage easement running diagonally across the back third of the pad, tied to the center's original detention pond. It wasn't on the broker's site plan. It wasn't on the aerial we'd pulled off the county GIS either, because the county's parcel layer hadn't been updated since the center was built in 2014 and the easement was recorded two years later when the outparcel got carved off.

That easement didn't just eat square footage. It cut the stacking lane short by about eleven feet, which meant the drive-thru no longer met the user's own stacking requirement without moving the building six feet closer to the front setback. Moving the building six feet closer to the front setback meant we were into the sign easement. The civil engineer's first redline took three weeks to come back, and by the time it did, the user's regional real estate committee had moved on to a site in the next market over.

What gets me about this one isn't that the easement existed. Easements show up. What gets me is how late we found it. We'd done a drive-by, pulled the county assessor record, run a demographic snapshot, and looked at the site plan the broker handed us, and none of that touches recorded easements that postdate the original plat. You find those in title, and title doesn't come back until you're already deep into due diligence, with an engineer on retainer and a clock running on the LOI.

I've started asking, on every pad site now, what's built on the ground right now, not what the site plan from 2014 says should be there. Detention ponds get regraded. Access easements get added when an outparcel sells off. A loading area on the back of the anchor can creep closer to a shared property line than the recorded plat shows. None of that shows up in a drive-by unless you know exactly where to stand, and none of it shows up in a parcel database that's three years behind the county's own recorder.

That's the gap a current overhead look closes, before you've committed engineering hours to a site that's going to fight you on access or detention. I've been running a quick parcel profile off current satellite imagery of the site as a first pass now, before anything goes to the civil engineer, just to see what's actually built and paved on the ground today. It won't catch a recorded easement that isn't visible from above. But it will catch the drainage swale that's wider than the plat shows, or the parking field that's already been restriped to fit something the original site plan never anticipated, and that's usually enough to know whether the deal is worth the engineering spend at all.

The pad site eventually died, user walked, broker found someone else. We still run the comp sheet on it in training now, mostly as a reminder that the site plan in the deal package is a snapshot of someone's intentions, not a survey of what's there. If you want a current read on a candidate site before you put an engineer on retainer, that's the whole reason this thing exists.